Region 5 - Natural Resource Open Consultation Information

Return to Previous Page

Contact the Consultation Team

Project Name & Short Description

Company

Approx. Location

Notes

Trans Mountain Expansion (TMX)Approved - expansion of existing system, and includes approx. 987 km of new pipeline, new and modified facilities, such as pump stations and tanks, and the reactivation of 193 km of existing pipelineTrans Mtn Pipeline ULCVancouver to Merrit (total length from Vancouver to Edmonton)

 

 Regions involved: 2, 3 and 5

  • Oct 19, 2022 - review of groundwater monitoring program complete
  • Jan 2023 - review of hydrostatic testing plans for 5A and 5B complete.
  • May 10, 2023 - review of Preliminary Caribou Habitat Offset Measures Plan complete.
  • May 30, 2023 - review of hydrostatic testing plan for spread 6/7A.
Sunrise Expansion Project - addition of pipeline loops and compressor station to increase capacityEnbridgeChilliwack to Merritt (total from Chilliwack to Chetwynd)

Regions involved: 2,3,5 and 7

  • Interactive project website: https://www.sunrise-program.com/
  • Jun 5, 2023 - Review of 2023 environmental field work complete.
  • Apr 24, 2023 - Project information package available for review.
Summit Lake PG LNG Project - construction of LNG facility. Meant to produce up to 2.7 million tonnes of LNG/yr and capacity of up to 200,000 cubic metres of LNGJX LNG Canada30 km north of Prince George

Regions involved: 5 & 7

  • Jan 30, 2024 - Initial project description submitted to the Impact Assessment Agency of Canada